Members in Attendance: Michael Panetta, Bo Rhyne
What was done (specifics): Pancake jumper cables fabricated, first jumper cable connected
What was not finished today: Finish jumper cables
Action items for next week: Finish jumper cables, install front and pancake boxes
Needed supplies/support: 1/0 Flex Cable, Conduit?
March 15, 2012
Members in Attendance: Michael Panetta, Bo Rhyne
What was done (specifics): Pancake holes drilled, back Linex plates made, back packs placed, intermediate connectors tested
What was not finished today: Pancake jumper cables fabricated, other jumpers fabricated
Action items for next week: Complete jumper cables
Needed supplies/support: Conduit?
March 1, 2012
Members in Attendance: Michael Panetta, Bo Rhyne
What was done (specifics): Configurations updated, all battery voltages checked
What was not finished today: Make jumper cables, drill holes
Action items for next week: Build and connect jumper cables
Needed supplies/support: One aught cable, cable terminals, solder pellets, foam?
Feb 23, 2012
Members in Attendance: Michael Panetta, Bo Rhyne
What was done (specifics): All series connections completed
What was not finished today: Drill remaining holes
Action items for next week: Connect jumper cables if ready
Needed supplies/support: One aught cable, fuse
Feb 16, 2012
Members in Attendance: Michael Panetta, Bo Rhyne
What was done (specifics): Started assembling battery configurations
What was not finished today: Complete configurations
Action items for next week: Complete configurations, connect configurations in series
Needed supplies/support: One aught cable, conduit, fuse
Feb 9, 2012
Members in Attendance: Michael Panetta, Bo Rhyne
What was done (specifics): Finished attaching busbars to battery packs, began to assess final battery layout and cabling
What was not finished today: Assembly of individual packs in box configurations
Action items for next week: Configure battery packs, make series connections
Needed supplies/support: Long bolts for series connectors, few feet of one aught cable, conduit
Feb 2, 2012
Members in Attendance: Michael Panetta, Bo Rhyne
What was done (specifics): All busbars were sanded to improve conduction, about half of the busbars were reattached to the individual battery packs
What was not finished today: Completing the reattachment of busbars
Action items for next week: Finish attaching busbars, assemble packs into final configuration, prepare to install boxes
Needed supplies/support: Front battery box needs Line-x by two weeks
26 Jan 2012
Members in Attendance: Michael Panetta
What was done (specifics): Battery packs were removed from the parallel charging storage and all busbars were removed.
What was not finished today: None
Action items for next week: Assembling packs into final configuration for each box. Scuffing busbars and reattaching each pack in parallel.
Needed supplies/support: Large tie-wraps.